Wastewater Improvements Project

Town of Osgood, Indiana

Project Background

The Town of Osgood, Indiana, built a wastewater treatment plant in 1997, but there were issues that were not addressed with the original design. High Inflow & Infiltration in the sanitary sewer system resulted in high flows that required the reporting of non-compliance to IDEM.  The performance of the wastewater treatment plant was also compromised due to high wet weather flows and, in some instances, Ammonia, TSS, and BOD effluent limitation violations occurred.

The Council knew they had to address future growth to the utility, aging equipment, and compliance issues while still meeting the needs of the community without a negative economic impact. Commonwealth Engineers developed plans for the upgrade of the Utility and assisted the Town of Osgood with securing federal, state, and regional grant funds that minimized the need to raise rates for residents.

Project Highlights

The project consisted of wastewater collection system rehabilitation and wastewater treatment plant (WWTP) improvements directed toward increasing operational efficiency and increasing peak wet weather flow rate capability by providing offline flow equalization.

Baffle walls were constructed in the Influent and RAS/WAS wet wells to correct poor hydraulic conditions and extend pump life. Energy efficiency improvements included VFD-controlled influent pumps and RAS/WAS pumps, VFD-controlled oxidation ditch rotors based on oxygen concentration, and separate blowers for each digester with VFD control again based on oxygen concentration. A new septage receiving station was constructed to accept material from the Town’s sewer cleaning truck. A sludge bagging station was constructed as a secondary means of sludge disposal whenever the land application isn’t feasible. Digester concrete repair was performed to extend service life. A new SCADA system was installed to control all the new energy-efficient equipment. Weather station equipment was installed at the WWTP and incorporated into the SCADA and alarming systems affording operations staff efficient and accurate indicators to prepare for and address wet weather events. Other improvements include a UV unit roof, outfall observation platform, influent screen repairs, polymer feed system, replacement tank sensors, flow meters, electric access gate, and drive paving. Additional electrical, mechanical, and site work was performed in order to support the improvements listed above.

The sewer system rehabilitation work consisted of manhole rehabilitation using cementitious lining and pipeline rehabilitation using a cured-in-place pipe liner.

Major Project Components

  • 0.5 MG Equalization Tank
  • Influent & RAS/WAS Pumps
  • Digester & EQ Blowers
  • VFD Controlled Oxidation Ditch Rotors
  • Septage Receiving Facility
  • Polymer Feed System
  • Sludge Bagging System
  • SCADA System
  • Digester Concrete Repair

Additional Projects

Wastewater
Wastewater & Stormwater Utility Planning Improvements – Arcadia, Indiana
Project Need PER was developed to outline capital improvements necessary to address anticipated Early Warning Sewer Ban issues as a result of hydraulic overload. PER developed to modify the existing… Read More
Wastewater
Wastewater Treatment Plant Rehabilitation Owensboro, Kentucky
Project Highlights Upgrade oxidation ditches to BNR process with turbo blowers Rehabilitation of structures & process equipment, including concrete tanks, clarifier equipment, pumps, the UV system, and the PAA system… Read More
Potable Water
Water Utility Improvements Project – Division A – Water Treatment Plant – Arcadia, Indiana
Project Highlights: OCRA funded Installation of a new settling tank ladder Replacement of the aerator blower Replacement 4-inch actuated butterfly valve Backwash flow meter Project Description: The project includes, but… Read More
Potable Water
Water Utility Improvements Project – Leavenworth, Indiana
Project Highlights: OCRA and SRF Funds – Total Grant / Loan Forgiveness $1,485,000 and $85,000 Loan Installation of a new 65,000 glass-fused-to-steel tank with an internal mixer Replacement of booster… Read More
Potable Water
Water Utility Improvements Project – L&M Water Utility, Losantville, Indiana
Project Highlights: OCRA Funded SRF Funded Distribution System Improvements Regional Project Project Description: The L&M Regional Water District constructed a new water main loop around the town of Losantville to… Read More
Wastewater
Wastewater Treatment Plant Improvements – Greenfield, Indiana
Project Need Originally constructed in the 1960s, updated and expanded through the 2000s Includes one (1) main activated sludge wastewater treatment facility and two (2) trains of Actiflo high-rate settling… Read More
Potable Water
Water Utility Improvements Project – St. Bernice Water Corporation, Clinton, Indiana
Project Highlights: Booster station improvements Distribution system improvements Service line replacements Customer meter replacements Storage tank repairs New administration building SRF & RD Funding Project Description: St. Bernice Water Corporation… Read More
Wastewater
Inflow and Infiltration Project – Spencer, Indiana
Project Highlights Gravity sewer New manhole installation Pavement restoration OCRA Funded The Spencer Inflow and Infiltration project rehabilitated select sections of the Town’s gravity sewer collection mains, ranging in size… Read More
Potable Water
Water Utility Improvements Project – Reelsville Water Authority, Reelsville, Indiana
Project Highlights: 4-inch water main 6-inch water main New pre-engineered metal storage building Installation of pressure-reducing valve bypass Distribution System Improvements  The project includes but is not limited to installing… Read More