Commonwealth Engineers, Inc. (Commonwealth) performed value engineering and construction oversight/inspection for the noted WWTP Improvements Project.

Efforts commenced with our Value Engineering (VE) Team. This VE Team was tasked with developing cost-saving recommendations consistent with the project goals and objectives as well as the identification of areas of concern with the design (by others) that merited the Town’s attention and consideration.

The VE Team consisted of highly qualified Professional Engineers, a Master Electrician/Instrumentation and Control Specialist, and a Construction Estimator experienced and specialized in municipal public works wastewater projects of this nature. The Team evaluated project components integral and related to the published design and identified in excess of $500,000 in cost savings opportunities (which was realized at project bidding). The VE Team also identified and addressed several potential constructability issues as well as clarifying work items required to ensure accurate bidding.

Major project work elements included the following facilities and equipment: mechanical fine screen, sewage pumps, grit removal facilities, alum building, rehabilitation of the oxidation ditch, flow split structure, secondary clarifiers, chlorination facilities, dechlorination facilities, and meter structure. The work also included plant access drive, paving, yard piping, process piping, demolition, excavation, dewatering, regrading, site restoration, coatings, electrical work, instrumentation and control, clean-up, and all other related work and appurtenances necessary to complete the work for the Fairmount Wastewater Treatment Plant Expansion.

Commonwealth’s Construction Engineering and Inspection efforts resulted in the Town retaining the majority of the initially budgeted construction contingency funds, which allowed us to solicit the use of over $250,000 in remaining funds for additionally required wastewater utility improvements and purchases.

 

Additional Projects

Wastewater
Wastewater Treatment Plant Improvements – City of Berne, Indiana
The Problem The City of Berne operates a Class II, 0.683 MGD controlled discharge waste stabilization lagoon facility consisting of a 16.42-acre lagoon (#1), a final 21.15-acre lagoon (#2), two… Read More
Wastewater
Wastewater Treatment Improvements – Town of Syracuse, Indiana
The Problem Commonwealth was hired to investigate and provide solutions to an underperforming wastewater treatment system for their oxidation ditches, which was also impacting performance in their clarifiers requiring frequent… Read More
Potable Water
Water System Improvements – Town of Flora, Indiana
Water System Improvements Town of Flora, Indiana Commonwealth Engineers worked with the Town of Flora on a two-part project to make improvements to their water system. Division “A” – Water… Read More
Wastewater
Long Term Control Plan Improvements – City of Crown Point, Indiana
Commonwealth Engineers performed a Long Term Control Plan improvements for the City of Crown Point. It included: ANDERSON POND PROJECT The Crown Point Anderson Pond Project is a Long Term… Read More
Wastewater
Long Term Control Plan & Sewer System Modeling – City of Madison, Indiana
Long Term Control Plan & Sewer System Modeling City of Madison, Indiana Commonwealth Engineers performed a Value Engineering / Alternatives Assessment to the City’s CSO Collection System Improvements Project. Coordinated… Read More
Potable Water
Water System Improvements Project – Town of West Terre Haute, Indiana
A Preliminary Engineering Report and Environmental Report were conducted to address West Terre Haute’s water system concerns.  Reports were completed in compliance with USDA Rural Development/State Revolving Fund Standards to… Read More
Wastewater
Long Term Control Plan Improvements Project – City of Nappanee, Indiana
Long Term Control Plan Improvements Project City of Nappanee, Indiana CSO Interceptor and Wet Weather Treatment and Storage Facilities Project: This project provides collection and treatment of excessive combined sewage… Read More
Wastewater
Wastewater Treatment Plant Improvements – Town of Fairmount, Indiana
Wastewater Treatment Plant Improvements Town of Fairmount, Indiana Commonwealth Engineers, Inc. (Commonwealth) performed value engineering and construction oversight/inspection for the noted WWTP Improvements Project. Efforts commenced with our Value Engineering… Read More
Stormwater
Crown Point Sewer Improvements Project – City of Crown Point, Indiana
Crown Point Sewer Improvements City of Crown Point, Indiana As part of the Long Term Control Plan, the City of Crown Point continues to find grant funding and savings options… Read More