Commonwealth Engineers worked with the Town of Flora on a two-part project to make improvements to their water system.

Division “A” – Water Treatment Plant

The project includes but is not limited to general improvements to the Town of Flora’s Water Treatment System and Distribution System. The work includes the replacement of existing high-service pumps and well pumps, the replacement of vertical pressure filters, a new disinfection system, the replacement of existing meters, and new customer meter heads. All work is to be completed with equipment in place and shall include all other work required for the intended operation and for the completion of the project.

Division “B” – Elevated Storage Tank Improvements

The work includes but is not limited to repairs to the two (2) existing elevated storage tanks, including exterior overcoating, cathodic protection, roof vent, roof railing, sidewall ladder and platform installation, miscellaneous safety improvements, and all other ancillary components required for a complete and operational system.

Any questions or any concerns that I had, Commonwealth – and their engineers and support group – was always there for me.”
Ron Fritz, Water Plant Operator | Flora, IN

Additional Projects

Wastewater
Inflow and Infiltration Project – Spencer, Indiana
The Spencer Inflow and Infiltration project rehabilitated select sections of the Town’s gravity sewer collection mains, ranging in size from 8 to 15 inches in diameter. The work includes cleaning… Read More
Potable Water
Water Utility Improvements Project – Maysville RWSD
Water Utility Improvements Project – Maysville Regional Water & Sewer District Division A – Water Main Extension The project includes but is not limited to a water main extension including… Read More
Potable Water
Water Utility Improvements Project – Gaston, Indiana
The project includes but is not limited to the replacement of selection sections of the Town’s water mains with a new 6-inch diameter water main. The work included the replacement… Read More
Wastewater
Wastewater Treatment Plant Rehabilitation Owensboro, Kentucky
Project Highlights Upgrade oxidation ditches to BNR process with turbo blowers Rehabilitation of structures & process equipment, including concrete tanks, clarifier equipment, pumps, the UV system, and the PAA system… Read More
Wastewater
Wastewater Treatment Plant Improvements – Greenfield, Indiana
Project Need Originally constructed in the 1960s, updated and expanded through the 2000s Includes one (1) main activated sludge wastewater treatment facility and two (2) trains of Actiflo high-rate settling… Read More
Wastewater
West Side Interceptor Improvements – Richmond, Indiana
Project Highlights Replace gravity sewers Collection system improvements Reduce combined sewer overflows Project Description The Richmond Sanitary District recently finished constructing over $6 million in collection system improvements, which involved… Read More
Wastewater
Wastewater Treatment Improvements – Syracuse, Indiana
The Problem Commonwealth was hired to investigate and provide solutions to an underperforming wastewater treatment system for their oxidation ditches, which was also impacting performance in their clarifiers, requiring frequent… Read More
Potable Water
Water System Improvements – Flora, Indiana
Water System Improvements Town of Flora, Indiana Commonwealth Engineers worked with the Town of Flora on a two-part project to make improvements to their water system. Division “A” – Water… Read More
Wastewater
Long Term Control Plan Improvements – Crown Point, Indiana
Commonwealth Engineers performed a Long Term Control Plan improvements for the City of Crown Point. It included: ANDERSON POND PROJECT The Crown Point Anderson Pond Project is a Long Term… Read More