Greenfield, IN WWTP Improvements Update
The new WWTP for the City of Greenfield is just three months into a 24-month schedule and progressing nicely. The base mat for the SBR is complete and walls are moving along quickly. Once complete this will be the largest SBR in the State of Indiana and will include a new Influent Pump Station, Headworks with grit removal, four SBRs with a sludge holding tank, UV disinfection, a sludge dewatering building with a centrifuge, and a new administration building. To date, through collaboration between Commonwealth Engineers, Inc and the contractor F.A. Wilhelm Construction, the project cost has been reduced to less than the original bid amount.